NEWS RELEASE ISSUED JOINTLY BY HIGHLANDS AND ISLANDS ENTERPRISE AND BALFOUR BEATTY
With the snowsports season now over, multiple teams from contractor Balfour Beatty, appointed by Cairngorm Estate owner Highlands and Islands Enterprise (麻豆精选), are set to be deployed on the mountainside.
A prime area of focus will be hundreds of 鈥榮carf joints鈥 linking beams and piers along the 1.7km viaduct. These were installed as part of a major reinstatement programme that ran for just over two years from November 2020.
In addition, testing is under way on tensioning works to beams and diaphragms that were also installed as part of the reinstatement programme and remedial action will be taken as required.
The funicular was initially withdrawn over safety concerns in October 2018, but came back into service in January 2023.
In August of that year, however, the service was again stopped after several scarf joints were found to be below the specified tension.
Hector MacAulay MBE, Managing Director of Balfour Beatty鈥檚 Regional business in Scotland, said: 鈥淲e are working hard to complete this programme of remedial works as quickly as possible, deploying multiple teams simultaneously to safely reinstate this unique attraction and resume service before the next winter snowsports season.鈥
Stuart Black, Chief Executive of Highlands and Islands Enterprise, said:聽 鈥淏alfour Beatty鈥檚 commitment to concluding these important works over the coming months is very welcome.
鈥淭his is still a challenging period for Cairngorm and we want to thank all the loyal supporters who continue to visit and enjoy all that the mountain estate has to offer throughout the year while work is ongoing to bring the funicular back.鈥
The funicular viaduct is essentially a series of 94 linked bridges of varying heights, supporting a railway that ascends Cairn Gorm to an altitude of over 1,000m.
Originally opened in 2001, it operates two carriages carrying visitors between the Cairngorm base station and Ptarmigan building, which houses a restaurant, shop, exhibition and viewing platform.
During winter, it is the main form of uplift to enable skiers and snowboarders to access higher parts of the mountain.
Cairngorm Mountain remains open while the programme of remedial works is under way, offering a range of family-friendly activities and catering choices in a stunning natural environment.
Related Articles
Annual maintenance and remediation work confirmed for Cairngorm funicular
Cairngorm Mountain (Scotland) Ltd has confirmed dates for essential annual maintenance on the funicular railway.
New chief executive for Cairngorm Mountain
An adventure sports and tourism specialist is set to take on the top job at one of Scotland’s leading outdoor attractions.
Limited space for businesses on Digital Tourism 麻豆精选 programme
Businesses in the tourism sector and its supply chain in the Highland Council area are being encouraged to secure a place on the Digital Tourism 麻豆精选 Programme.
New tenant welcomed to Inverness Campus
The move will help facilitate the company’s further growth. Its corporate and compliance team of ten will relocate to Aurora House, with the company’s operational base remaining in Beauly.
Luing community project secures 麻豆精选 funding
The Isle of Luing Community Trust owns and operates the Atlantic Islands Centre and is leading the £87,320 improvement project.
麻豆精选 approves further £863k for Inverness Castle project
The additional funding brings 麻豆精选’s total investment in the project to £2.863m.
Cairngorm Mountain Railway returns to service
The funicular railway at Cairngorm Mountain resort is set to return to service on Thursday 27 February.
Expansion of luxury self-catering on Great Cumbrae
Jack Alt Stays to develop three more high-end cabins